Part 3: The Basement Bathroom.
The area of the basement where the bathroom would go was already determined because the sewer drain plumbing and venting were out in when the house was built. This meant that the placement of the tub, toilet and general area of the vanity was pretty well fixed. Given that I decided to keep the bathroom modest in size and save the extra square footage for the rest of the basement.
I really had hoped to get a one piece tub and shower enclosure into the basement but with the stairwell already finished it wouldn’t have fit down the steps… instead I chose a 2 piece unit. A tub and a single piece surround.
Continue on for the 25 images that shows the progress of the bathroom…

Cardboard shows drain plumbing locations / PVC is the vent stack / Tub will go between the windows.

Framing of the back of the Tub / Tub set into framed room / Bath Fan installed

Heat duct into bathroom / Plumbing and clean-out access / Moisture resistant drywall

Electrical wiring in place / patching of drywall

Bath fan opening / mudding of drywall complete / bath accessories

The painting of the room begins!

Tile backer down / Loose fitting the tile / Tile down but not grouted